Cable MOQ and lead time

Minimums and lead times on cable are set per construction and per plant, not by a single rule. These are the typical ranges seen in partner plant listings and how the desk turns them into dates you can plan around, always confirmed in writing for each order; the MOQ explainer covers the reasoning.

Request a quote

Short sample lengths of power cable and a trial drum beside full export drums for an MOQ and lead time comparison

Why cable MOQs exist

A cable line has to be set up for each construction: conductor stranding, insulation die, core colours, cabling, sheath compound, print text. Setting up, running in and testing take time and scrap material whether the run is 100 m or 10 km. A plant's minimum reflects that set-up cost and the length it can sell or use from a partial run. Stock constructions that a plant runs every week carry lower minimums than a special sheath colour or an unusual core count. The figures below come from partner plant listings and supplier terms. They are typical ranges, not an industry standard, and the exact figure is confirmed in writing for each order.

Typical MOQ by line

Typical minimum order ranges (plant listings, confirmed per order)
LineTypical MOQNotes
LV power cable, armoured cableAround 500 m per sizeSome plants accept 100 m for stock sizes
Control cableAround 1,000 m per sizeMany core counts; numbered cores set per run
Solar PV cableFrom 100 m up to 500-2,000 mVaries widely by plant; red and black often ordered together
Cat6 LAN cable50-100 boxes of 305 mA few plants list 10 boxes
Stock samplesUp to about 5 m, often freeFreight paid by the buyer
Custom sample or trial drum10-50 m, paidFor a custom construction, colour or print

Small orders are usually priced higher per metre than full runs, because set-up and testing are spread over less cable. MV cable, fibre cable and special constructions are quoted per enquiry. Mixing several sizes in one order is normal; the MOQ usually applies per size, not per order.

Distributors restocking common sizes can often meet minimums by grouping sizes a plant already runs. Marketplace sellers and DTC brands launching a new box design usually reach the minimum through the packing rather than the cable, because own-brand boxes and wraps carry their own print minimums. Project buyers normally exceed the cable minimum but need lengths cut to their schedule.

What drives lead time

The desk does not publish standard lead times in days for power or fibre cable, because four things move them on every order.

  1. Copper booking: copper and aluminium make up around 80% of cable cost according to listed company filings, and quotes follow the copper price plus a processing fee. Once the order is confirmed and the deposit is paid, the plant books metal against the quote. Quote validity is usually short, counted in days and written on the quote, so a delayed decision can mean a re-quote.
  2. Production slot: the plant schedules the run around its other orders and its line set-ups. Medium voltage and armoured cable go through more process steps, such as screening, armouring and an extra sheath, so they need longer slots (inference from the process, confirmed per order).
  3. Routine tests: conductor resistance and voltage tests on every drum, partial discharge on MV cable to IEC 60885-3, and for fibre the OTDR traces per drum. Witnessed tests need a date agreed with you or your inspector.
  4. Drums and packing: wooden drums are made to order, and the drum maker's figure is 2 to 4 weeks. Own-brand boxes and labels have their own print time.

Fibre cable lead time is set by fibre and tube scheduling at the plant and confirmed per order. For Cat6, plant listings show roughly 5 to 25 days up to about a month, depending on stock and box artwork.

Samples and trial drums

A stock sample is a short length of a construction the plant already makes, useful for checking print, colour and dimensions. A paid trial drum of 10 to 50 m is made to your specification and is the right step before a private label launch or a new construction. Solar cable samples are often ready within 3 to 7 days after payment at one listed plant. See samples and trial orders.

How lead time is confirmed

The desk issues a written schedule with the order confirmation: deposit date, copper booking, drum delivery, production window, test dates, inspection and loading. If a step moves, the schedule is re-issued in writing. For large projects with phased deliveries, a copper price adjustment formula can be agreed instead of re-quoting each phase; see lead time planning and the pricing guide.

Send your sizes and metres per size through the quote form, and the desk returns the MOQ and a schedule for each line in writing.

Questions buyers ask

Q01What is the minimum order for power cable?

Partner plant listings commonly show around 500 m per size for LV and armoured cable, with some plants accepting 100 m for stock sizes and control cable often around 1,000 m. These are typical ranges; the exact minimum is confirmed in writing for each order.

Q02Why can you not give a fixed lead time?

Power cable lead time depends on copper booking, the plant's production slot, routine testing and drum making, which change with every order. The desk issues a written schedule with the order confirmation and re-issues it in writing if any step moves.

Q03Are samples free?

Short stock samples of up to about 5 m are often free, with freight paid by the buyer. Custom constructions, colours or print need a paid sample or trial drum of 10 to 50 m. Terms are set per plant and confirmed in writing.

Q04Can several sizes share one MOQ?

Usually the minimum applies per size or construction, because each one needs its own set-up. Mixing many sizes in one order is common, and the desk can split them across partner plants and consolidate for loading.

Q05Why do small orders cost more per metre?

Set-up, scrap and testing are similar for short and long runs, so they are spread over fewer metres on a small order. Small-order prices are usually higher; the quote shows the price per size so you can compare run lengths.

RFQSend the construction or standard you need, cross-sections, total metres and drum lengths, the reports your market asks for and the destination port. The desk replies in writing with matched factories, a spec sheet and the reference MOQ.