Cable sourcing process, from RFQ to loading

Eight steps, each closed in writing before the next one starts. The desk coordinates partner plants in the clusters that make your construction, and you see the spec sheet, test records and inspection report before the balance is paid; the China sourcing overview gives the background.

Request a quote

Cable spec sheet, sample lengths and a drum plan laid on a desk during the cable sourcing process review

The process at a glance

Buying cable well is mostly about removing ambiguity before copper is booked. Once metal is bought and the line is set up, changes cost time and money. The desk's process puts the decisions in the right order and closes each one in writing, so that the plant, the inspector and you work from the same documents.

Eight steps from RFQ to loading
StepWhat happensClosed by
1. RFQYou send constructions, sizes, metres, standard, market, packing and portDesk confirms the enquiry is complete
2. ShortlistThe desk matches partner plants in the right cluster and checks their reports and listingsShortlist and quote sent to you
3. Spec sheetEvery layer, print text, drum plan, tests and documents fixedSpec sheet signed by you
4. Sample or trial drumStock sample or paid 10-50 m trial for custom constructionsWritten sample approval
5. Copper bookingDeposit paid; plant books copper or aluminium against the quoteOrder confirmation and schedule
6. ProductionRun scheduled; routine tests recorded per drumTest records sent to you
7. InspectionPre-shipment check of length, print, dimensions, records and packingInspection report
8. LoadingDrums loaded, chocked and lashed; documents issuedBalance paid, documents released

Steps 1 and 2: RFQ and shortlist

A good RFQ names the construction rather than a product name: voltage rating, conductor material and class, cores and size, insulation and sheath, armour if any, the standard and the market. Add metres per size, packing and run lengths, the port and any test or witness requirements. The RFQ checklist lists every field. The desk then shortlists partner plants in the cluster that makes the construction, for example Yixing, Ningjin or Wuwei for power and special cable, Wuhan or Wujiang Qidu for fibre cable, and checks their routine and type test reports and any listing held for that construction in the certifier's public database. See factory audit.

Steps 3 and 4: spec sheet and sample

The spec sheet is the contract for the cable. It fixes conductor class and resistance limit, insulation and sheath thickness, colours, print text, drum type and length per drum, the routine tests per drum, any witnessed tests and the document pack. For a stock construction a short sample is usually enough to check print and dimensions. For a new construction, colour or private label a paid trial drum of 10 to 50 m is made to the spec sheet and approved in writing; see samples and trial orders.

Step 5: copper booking and price

Cable is quoted as the metal price plus a processing fee, because copper and aluminium make up around 80% of the cost according to listed company filings. The quote states its validity, usually a matter of days. After you confirm the order and pay the deposit, the plant books metal against the quoted price. For long or phased projects a copper price adjustment formula linked to LME can be agreed instead, as is common in European contracts. As background only, LME three-month copper reached a record USD 14,875/t intraday on 2026-09-10 (Fastmarkets) and stood near USD 14,315/t on 2026-10-21 (Investing News); the desk does not forecast prices. See the pricing guide.

Steps 6 to 8: production, inspection, loading

During production the plant records conductor resistance and voltage tests on each drum, partial discharge on MV cable, and OTDR traces on fibre drums. You receive the records as they are issued. Before loading, the desk's inspector checks a sample of drums against the spec sheet using ISO 2859-1 sampling where agreed: length by metre marks, print, overall diameter, insulation thickness on cut ends, end caps and drum tags. Details are on testing and inspection; loading and documents are on logistics and shipping.

Payment terms

  • 30/70 T/T: 30% deposit by telegraphic transfer to start copper booking and production, 70% balance before shipment once test records and the inspection report are accepted. This is the most common arrangement.
  • L/C: a letter of credit for larger or first orders, with the documents the bank must see written into the credit, such as the inspection report and packing list by drum.

Payment terms, Incoterm and schedule are written on the order confirmation. Typical minimums and how lead time is set are on MOQ and lead time. Start with the quote form; a BOQ in any format is accepted.

Questions buyers ask

Q01What should a cable RFQ include?

The construction (voltage, conductor material and class, cores and size, insulation, sheath, armour), the standard and market, metres per size, packing and run lengths, the destination port and any witness or test requirements. Naming the construction rather than a product name avoids most quote mismatches.

Q02When is copper booked?

After you confirm the order against a valid quote and pay the deposit. The plant then buys metal at the quoted basis. Because quotes are tied to the copper price, their validity is short, usually counted in days and written on the quote.

Q03What payment terms are common?

A 30% T/T deposit and 70% balance before shipment is the most common, with the balance paid after test records and the inspection report are accepted. A letter of credit can be agreed for larger or first orders, with the required documents named in the credit.

Q04Do we have to order a trial drum?

Not always. For stock constructions a short sample is usually enough. For new constructions, colours, print or private label packing, a paid 10 to 50 m trial drum made to the spec sheet is the safer step before full production.

Q05Who inspects the cable before shipment?

The desk arranges a pre-shipment inspection against the spec sheet and test records, and you may also appoint your own inspector or a third-party agency. Witnessed tests at the plant can be scheduled on dates agreed in writing.

RFQSend the construction or standard you need, cross-sections, total metres and drum lengths, the reports your market asks for and the destination port. The desk replies in writing with matched factories, a spec sheet and the reference MOQ.